Updated Streets and Sidewalks page
June 18, 2013
All,
This is the 7th
weekly update on the Sunset Street Wide Sidewalk project. Through last week, the contractor has used 19
of their allotted 45 "working days".
Work last week focused on the segment south of Oakcrest Avenue preparing
the grade for the new sidewalk alignment, rebuilding the street curb on the
south corner of Oakcrest, and beginning demolition work of fence and retaining
wall at the Sunset/Benton intersection.
The contractor
indicates planned work for this week includes:
- Storm sewer work and fire hydrant relocation between Highland and Oakcrest.
- Continue demolition and grading at the Sunset/Benton corner to prepare for new retaining wall installation.
- Paving sidewalk south of Highland Drive, and perhaps some sidewalk just south of Oakcrest Avenue.
- Continued work by Mid-American to set new poles and move their lines to the new poles, and hopefully appearances by Mediacom, Qwest, and Windstream to move their overhead lines from the old poles to the new poles so that Mid-American can remove the old poles.
Please let me
know if you have any questions, thanks.
Josiah D.
Bilskemper, P.E.
Shive-Hattery,
Inc.
2834 Northgate
Drive
Iowa City, IA
52245
(319) 354-3040

No comments:
Post a Comment