Monday, June 3, 2013

June 3, 2013

Updates to University Heights website:
Updated Streets and Sidewalks  page
June 3, 2013
All:

This is the 5th weekly update on the construction progress of the Sunset Street Wide Sidewalk project.  Due to the rain last weekend, and the on and off rain scattered throughout the week, the only items completed last week were a few tree removals and the installation of one utility pole by Mid-American.  Therefore, the contractor (and Mid-American Energy) is planning to focus this week on the same items that we listed from update #4 below.

Also, with today being the last day of school, the south section of the project (Oakcrest to Benton) will be available to the contractor beginning tomorrow (6/4). The contractor may get to this section of the project this week by closing the sidewalk and beginning removal of existing sidewalk.

On another note, the first University Heights Farmer's Market is this Tuesday, June 4th from 5pm - 7 pm at St. Andrew Church.  See attached poster for additional information.

Please let me know if you have any questions, thanks.

Josiah D. Bilskemper, P.E.
Shive-Hattery, Inc.
2834 Northgate Drive
Iowa City, IA 52245
(319) 354-3040

    No comments:

    Post a Comment