Updated Streets and Sidewalks page
July 22, 2013
All:
This
is the 10th update on the Sunset Street Wide Sidewalk project. Work completed last week included relocation
of one fire hydrant, and paving of several long stretches of sidewalk and curb ramps
south of Highland Drive, and south of Oakcrest Avenue. At the end of last week, work began at the
southwest corner of the Melrose/Sunset intersection with removal of existing
pavement.
The
contractor indicated they will be working on the following items this week:
1.
Melrose/Sunset
corner: relocate fire hydrant, prepare grade, pave new curb ramps and sidewalk
connection to the south.
2.
Remove
remaining tree trunks and grind stumps below grade.
3.
Prepare
new curb ramps and sidewalk connection at the northwest corner of Sunset/Oakcrest.
4.
Prepare
grade for new sidewalks and curb ramp at the Benton corner adjacent to the new
retaining wall.
5.
Begin
backfilling with dirt and topsoil adjacent to sections of sidewalk that have
already been paved.
At
this point, the weather forecast for the rest of the week looks promising. If the contractor can complete these work
items by the end of the week, we would expect to see almost all of the paving work
complete. Please let me know if you have
any questions, thanks.
Josiah
D. Bilskemper, P.E.
Shive-Hattery,
Inc.
2834
Northgate Drive
Iowa
City, IA 52245
(319)
354-3040