This is the 11th update on the Sunset Street Wide Sidewalk project. Work completed last week included installation of new fire hydrant and valves at the Melrose intersection, removal and grinding of stumps, and grading and backfilling along portions of the sidewalk paved the week before.
This week the contractor reports they will be focusing on preparing the dirt grade on all remaining sections of the sidewalk. This is at the Benton intersection, the Melrose intersection, the north side of the Oakcrest intersection, and a short segment between Highland and Oackrest. They plan to have the paving contractor back on-site at the end of the week to begin setting forms to pave these sections of sidewalk and curb ramps. They will begin paving some sections by Friday if they are ready, otherwise they will be back on-site the following Monday to pour all the remaining sections of sidewalk. They also plan to continue their grading and backfilling work throughout the week, and general site clean-up.
Please let me know if you have any questions, thanks.
Josiah D. Bilskemper, P.E. Shive-Hattery, Inc.
2834 Northgate Drive
Iowa City, IA 52245
(319) 354-3040

No comments:
Post a Comment